試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

An organization and a subcontractor have identified a potential positive impact to a project. The project manger is asked to develop a response in dealing with the positive impact. What does the project manager do?
A、Investigate options to create a risk sharing partnership with the subcontractor to manage opportunities.
B、Mitigate the risk to keep the project within scope.
C、Do nothing and comply with the project charter.
D、Transfer the opportunity to the project sponsor to develop the next steps.